Theory: Task Dependencies (or task Relationships): • Task Dependencies (or task Relationsh...
Theory: Fixed Duration, Fixed Units, Work – effort driven On or OFF: • Fixed Duration, Fixed Units, Work - e...
19 TIPS for setting-up the perfect project: • How to prepare, setup and manage the ...
/ @pieterrademeyer1 (Visit my Channel for Project Management topics and videos)
In this video project schedule example is used to explain the difference between Elapsed Time, Duration, and Effort (or Work).
Scheduling formula: Work (or Effort) = Duration x Resource Units
Elapsed time = calendar days (incl. weekends and public holidays)
Duration = amount of time required to complete a task (hours, days, weeks)
Units = number of resources assigned to a task (people, equipment, material)
Effort (or Work) = amount of effort required to complete a task (hours, days)